AAC Plant
Client : Parin Beton Amood
Services Provided : Civil, Mechanical, Electrical Works and Instrumentation.
Capacity : 1550 m3/day Duration : 24 months ------------------------------------------------------------------------------------------------------
Jam MEGA Olefin Plant
Client : Jam Petrochemical Copmapy
Services Provided : Civil Works (Except Foundations, Structures), Steel Structures, Mechanical Erection, Piping Installation, Electrical and Instrumentation Installation precommissioning and assistance in commissioning for the Unit.
Capacity : 1320 Kt/year Duration : 15 Months ------------------------------------------------------------------------------------------------------
Zave Cement Plant
Client : Zave
Services Provided : Civil Works
Capacity : 3500 ton/day Duration : 24 months ------------------------------------------------------------------------------------------------------
Olefin Plant
Client : Marun Company
Services Provided : Piling Fabrication and driving and construction of the foundation, superstructures including industrial buildings and Underground piping for the entire plant.
Steel Structures, Mechanical Erection, Piping Installation, Electrical and Instrumentation Installation and assistance in commissioning for the Unit.
Capacity : 1100 Kt/year Duration : 28 Months ------------------------------------------------------------------------------------------------------
Offsite Plant
Client : Marun Company
Services Provided : Construction of Civil Foundations, Superstructures, and industrial buildings including Under Ground Piping of the plant.
Steel Structures, Mechanical Erection, Piping Installation, Electrical and Instrumentation Installation and assistance in commissioning for the offsite.
Duration : 12 Months ------------------------------------------------------------------------------------------------------
Poly-Propylene Plant
Client : Marun Company
Services Provided : Construction of Civil Foundations, Superstructures, and industrial buildings of the plant.
Capacity : 300 Kt/year Duration : 12 Months ------------------------------------------------------------------------------------------------------
Amir Kabir Petrochemical Complex - Olefin Plant
Client : Amir Kabir Company
Services Provided : Pile Fabrication and driving, Construction of Civil Foundation, superstructure, Civil Works for the Tankage area and Industrial Buildings including Under ground piping for the Ethylene plant.
Capacity : 520 kt/year Duration : 14 Months ------------------------------------------------------------------------------------------------------
Amir Kabir Petrochemical Complex - High Density Poly-Ethylene Plant
Client : Amir Kabir Company
Services Provided : Construction of Civil Foundation, Super Structure including industrial buildings civil work for the entire plant.
Steel Structures, Mechanical Erection, Piping Installation, Electrical and Instrumentation Installation and assistance in commissioning for the Unit.
Capacity : 140 kt/year Duration : 18.5 Months ------------------------------------------------------------------------------------------------------
Amir Kabir Petrochemical Complex - Linear Low Density Poly-Ethylene Plant
Client : Amir Kabir Company
Services Provided : Construction of Civil Foundations, Superstructures including industrial, non-industrial buildings and underground piping.
Capacity : 300 kt/year Duration : 14 Months ------------------------------------------------------------------------------------------------------
Amir Kabir Petrochemical Complex - Poly-Propylene Plant
Client : Amir Kabir Company
Services Provided : Piling Fabrication, Construction of Civil Foundations, Superstructures, and industrial buildings including Under Ground Piping of the plant.
Capacity : 300 kt/year Duration : 12 Months ------------------------------------------------------------------------------------------------------
Booali Sina Third Aromatic Complex
Client : Booali Sina Company
Services Provided : Piling Fabrication and Construction of foundations and superstructures for the process and Offsite Area and utilities including Power Station, Cooling Tower Plant and Under Ground Piping and Construction and installation of Industrial and non-industrial buildings for the Plant.
Capacity : 1740 kt/year Duration : 12 Months ------------------------------------------------------------------------------------------------------
Shariati Combined Cycle Power Plant
Client : MAPNA
Services Provided : Construction of Civil Foundation, superstructure, and Industrial Buildings for the plant including Power House, Turbine Generator, H.R.S.G., Raw Water Tank, Neutralisation Tank, Oily Water Separator Tank, Evaporation Pond, Aux. Boiler, Aux. Services, Water Treatment, Control Room including Lighting & Under ground piping for the Plant.
Capacity : 100 Mw Duration : 20 Months ------------------------------------------------------------------------------------------------------
Khorasan Steel Complex
Client : Khorasan Steel Company
Services Provided : Construction of Civil Foundation, superstructure for the Rolling Mill, Melt Shop, Scrap Yard, Nitrogen Plant, Cooling Tower, Water Treatment, Control Room, Substations for the Plant including Under ground piping.
Capacity : 500 kt/year Duration : 26 Months ------------------------------------------------------------------------------------------------------
Khorasan Petrochemical Complex (Ammonia & Urea Plant)
Client : Khorasan Petrochemical Company
Services Provided : Construction of foundations and superstructures for the process and Offsite Utilities including Power Station, Water Treatment Plant and Under Ground Piping and Industrial and non-industrial buildings for the Plant.
Steel Structure, Mechanical Erection, Piping Installation, Electrical and Instrumentation Installation and assistance in commissioning for the offsite Utilities including Power Station, Compressed Air and Water Treatment Plant.
Capacity : 800 Kt/year Duration : 40 Months |
|
|
|